VMS Ventures and operating partner HudBay Minerals to commence...

  1. 1,002 Posts.
    lightbulb Created with Sketch. 2
    VMS Ventures and operating partner HudBay Minerals to commence production at the Reed Mine in 2013

    Summary of the Reed Mine’s Economic Assessment


    ? Initial production at Reed is expected by Q 4 - 2013 and will ramp up to full production of approximately 1,300 tonnes per day by Q1 - 2014.

    ? Average expected reserve ore grades of 3.83% copper, 0.48 g/t gold and 6.02 g/t silver, slightly better than PEA due to the exclusion of the inferred resources in the pre-feasibility study.

    ? Assumed metal recoveries in HudBay’s Flin Flon Concentrator of 94% copper, 58% gold and 62% silver.

    ? Average production in concentrate of approximately 17,000 tonnes per year of copper metal.

    ? Total operating costs estimated to average approximately $90 per tonne milled ($67 per tonne mining, $16 per tonne milling and $7 per tonne administration) over a five year mine life.

    ? Sustaining capital expenditures are expected to total approximately $52 million over the five year mine life.

    ? Pre-Feasibility pre-tax NPV (8%) of $57.4 million using weighted average metal prices of US$2.95/lb. for copper, US$1,269.09/oz. for gold and US$24.78/oz. for silver.




    Exploration is ongoing on the company’s other properties.

    Latest exploration news http://finance.yahoo.com/news/vms-ventures-announces-2013-winter-113000818.html

    2012 Reed Mine Development & Opening Ceremonies Slide Presentations Link

    http://vmsventures.com/Projects/Manitoba-Properties/VMSHudBayJointVentures/VMS-Ventures---HudBay-Joint-Venture-Project/default.aspx


    Symbols: VMS.V / VMSTF.OTC


    Website: http://www.vmsventures.com

 
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.