And yet another delay, now a whole year, will the demonstration plant ever become a reality?That is very much in doubt!:
Out of the Quarterly Activities Report March 2022:
"The lithium hydroxide production Demo Plant, (CLP-Demo Plant) also known as “LiLy”, is progressing
concurrently, with 95% of the required equipment ordered ahead of commissioning, which is expected
to start Q1 ‘23, with some delivery delays experienced by the purchasing team linked to current supply
chain issues related to the global geopolitical situation"
Previous post:
Vulcan keeps pushing back thecommissioning date of the demonstration plant ...
19.07.2021
"A pilot plant has been runningsince April. "At the beginning of next year, a demonstrationplant will go into operation that can produce tonnes in terms ofvolume," Kreuter added."
https://www.boerse-online.de/nachrichten/aktien/lithium-foerderer-vulcan-energy-denkt-an-boersengang-1030620249
10.12.2021
"Vulcan is planning to build ademonstration plant for lithium production at its Landau site, whichis expected to come on stream in the second quarter of 2022."
https://www.pressetext.com/news/20211210024
10/03/2022
"The demonstration plant, which isexpected to be operational in mid-2022, will consist of two parts:the DLE (direct lithium extraction) plant and the lithium hydroxideproduction plant."
https://research-hub.de/companies/research/Vulcan%20Energy%20Resources?date=2022-03-10&title=10.03.2022%20Energiekrise%20untermauert%20das%20Gesch%C3%A4ftsmodell%20-%20KAUFEN
21.04.2022
"In addition, Vulcan provided anupdate on progress with the construction of the demonstration plant,which is expected to be commissioned later this year."
https://www.wallstreet-online.de/nachricht/15342443-vulcan-abnahmevertrag-aufbau-demo-anlage-plan-kau
Vulcan keeps pushing back thecommissioning date of the demonstration plant ...
19.07.2021
"A pilot plant has been runningsince April. "At the beginning of next year, a demonstrationplant will go into operation that can produce tonnes in terms ofvolume," Kreuter added."
https://www.boerse-online.de/nachrichten/aktien/lithium-foerderer-vulcan-energy-denkt-an-boersengang-1030620249
10.12.2021
"Vulcan is planning to build ademonstration plant for lithium production at its Landau site, whichis expected to come on stream in the second quarter of 2022."
https://www.pressetext.com/news/20211210024
10/03/2022
"The demonstration plant, which isexpected to be operational in mid-2022, will consist of two parts:the DLE (direct lithium extraction) plant and the lithium hydroxideproduction plant."
https://research-hub.de/companies/research/Vulcan%20Energy%20Resources?date=2022-03-10&title=10.03.2022%20Energiekrise%20untermauert%20das%20Gesch%C3%A4ftsmodell%20-%20KAUFEN
21.04.2022
"In addition, Vulcan provided anupdate on progress with the construction of the demonstration plant,which is expected to be commissioned later this year."
https://www.wallstreet-online.de/nachricht/15342443-vulcan-abnahmevertrag-aufbau-demo-anlage-plan-kau
- Forums
- ASX - By Stock
- VUL megathread
And yet another delay, now a whole year, will the demonstration...
Featured News
Add VUL (ASX) to my watchlist
(20min delay)
|
|||||
Last
$4.89 |
Change
-0.120(2.40%) |
Mkt cap ! $920.2M |
Open | High | Low | Value | Volume |
$5.04 | $5.10 | $4.86 | $1.824M | 368.8K |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
1 | 1995 | $4.88 |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
$4.90 | 1014 | 2 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
1 | 1995 | 4.880 |
2 | 5205 | 4.870 |
6 | 11854 | 4.860 |
4 | 10160 | 4.850 |
4 | 14065 | 4.840 |
Price($) | Vol. | No. |
---|---|---|
4.960 | 5445 | 2 |
4.980 | 1907 | 1 |
5.020 | 10000 | 1 |
5.040 | 3491 | 1 |
5.050 | 35000 | 2 |
Last trade - 16.10pm 04/11/2024 (20 minute delay) ? |
Featured News
VUL (ASX) Chart |