    Hope you are right however based on my calculations we had to go back up to 1800m to recommence the sidetrack drilling I suspect we are now running at P70 which will not be unusual for the sidetrack drilling. To get down to the next stage will take 10 days based on current drill rate and then they will need the 9 5/8" casing point which is a few hundred meters from TD (top of last objective). The cement will need setting time at an estimate would be 2 days. Once this is completed it will take another 4-5 days to reach TD.

    All comment are welcome.