Hello to all on the MEO thread, last week I sent off a few emails to various contacts, glad to say I got a response from Shell today and the news is good as far as I'm concerned.
I will post the whole email thread but for obvious reasons will omit names, a nice buildup to the last paragraph...enjoy.
My initial email:
From: SAL Technical AU SAL
Sent: Saturday, 16 October 2010
To: SAL Technical AU SAL
Subject: OneShell.com Form Response
Re: W05-3 (WA-371-P) Concerto 3 Drilling
I am conducting research into drilling in the Browse Basin and ask if you can provide any guidance on when the Concerto 3 drilling is scheduled to conclude?
I disclose that I am a MEO Australia Ltd shareholder and trying to research and establish an approximate date that the Songa Venus may be released for the pending Artemis drill.
Kind regards,
xxxx
1st response:
Subject: FW: Shell Reference: xxxx RE: xxxx Form Response
Date: Mon, 18 Oct 2010 16:31:02 +0800
From: xxxx
To: [email protected]
Dear xxxx,
I have received your query and will follow it up for you. I hope to get back to you tomorrow.
Kind regards,
xxxx
My response:
From: [mailto:[email protected]]
Sent: Tuesday, 19 October 2010 5:19 AM
To: xxxx
Subject: RE: Shell Reference: xxxx RE: xxxx Form Response
Thankyou xxxx,
I have only this morning found out that the semi-submersible Songa Venus rig recently arrived on location to drill Shell's follow-up well to Octans #1 in AC/P41 in the Libra block so any information in regards to the duration of this drill, approximate date it is due for completion etc would be greatly appreciated.
Kind Regards,
xxxx
Email I received today:
Subject: RE: Shell Reference: xxxx RE: OneShell.com Form Response
Date: Wed, 20 Oct 2010 14:31:06 +0800
From: [email protected]
To: [email protected]
CC: [email protected]
Hi xxxx,
The drilling team tells me the rig will be at AC/P41 for about 30 days from now, so you should see the rig moving on mid-late November.
Kind regards,
xxx
So looks to be only a short drill so end of November is very much on the cards, don't rule out the possibility of Shell having it for another drill after that but it very much falls in line with MEO's guidance on the expected drill date so you would think we are "go" for launch mid to late November.
A big thanks to pocko & mrmoshe for some good accurate updates over the weekend on the "sv on the move??" thread that confirmed the location of the Rig at AC/P41 to give my response a bit more credibility.
Interesting days ahead,
Cheers
- Forums
- ASX - By Stock
- we are go for launch
Hello to all on the MEO thread, last week I sent off a few...
-
- There are more pages in this discussion • 58 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)