This is from thier schedule. Please keep in mind first hole took 5 months however if all goes well these are the timelines. Also we don't need approvals anymore we can just set casting and go straight to td.
Days of duration
Preparation and Construction: 4 to 6 days
Operation Perforation: from 4 to 15 (depending on the depth of the well and assuming ROP of 100 m / d)
Production tests: 10 days
Closing and abandonment: 5 days
The total schedule for a dry well may vary between 16 and 27 days, and in case of being discovered
from 23 to 34 days