Once final investment decision is made (estimated to be early 2015), LNG will received US$660 million + 66 million + 25 million = 751 million. (7 times the current market cap.=>Target SP: $2.4)
***In order to reach final investment decision:
1.Executed Tolling Agreements for a total of 3.4mtpa ( should be done by the end of this Year)
2.EPC ( by the end of this year)
3. Project Debt Financing Facility of US$1.540 billion (should be done by the 2nd or 3rd quarter of 2014, complex/ relatively more difficult process but with the help of Stonepeak => definitely possible)
4.30 years Lease Agreement with "port" ( should be done by 3rd Q of 2014, easily done)
5. A notice to proceed from FERC (possibly hardest to achieve, Given satisfying all the points before. This is possible by early 2015)
With all points satisfy = final investment decision, SP > $2.4.
It is interesting to see traders selling shares now. Good Luck to all.