    The original plan was the following:
    • Jun08 Mt Mulligan Access
    • Dec08 Mt Mulligan JORC Resource
    • Jun09 Mt Mulligan PFS
    The access as you know has been delayed as the draft Indigenous Land Use Agreement was exchanged at the beginning of the month. Going by the above timeline the JORC would be well on its way if not completed in 6 months.

    So I guess if access was granted soon then some results for the JORC would be available by this time, but completion by the end of this calendar year might be pushing it. By the end of financial year is my conservative target.

    The management will be working hard on this so I would also expect the PFS (Pre-Feasibility Study) to be available around this time also.
 