Production from double completed Sillaro 2dir well was operating...

  1. 14 Posts.
    Production from double completed Sillaro 2dir well was operating at its targeted production rate of 31,200m3/day from level A and will be increased further when
    level E is brought into production over the next week. Production from Sillaro 1dir is planned to follow.
    Over the next month the plant will be brought up to the planned full production rate of 110,000m3/day.
    That was 19th april so a month is up. Is Sillaro up to full production? When will we know? It must be real soon.
 
Add to My Watchlist
What is My Watchlist?
A personalised tool to help users track selected stocks. Delivering real-time notifications on price updates, announcements, and performance stats on each to help make informed investment decisions.
(20min delay)
Last
5.5¢
Change
-0.001(1.79%)
Mkt cap ! $63.74M
Open High Low Value Volume
5.6¢ 5.7¢ 5.5¢ $40.80K 737.8K

Buyers (Bids)

No. Vol. Price($)
1 70149 5.5¢
 

Sellers (Offers)

Price($) Vol. No.
5.7¢ 64913 1
View Market Depth
Last trade - 15.42pm 08/08/2025 (20 minute delay) ?
PVE (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.