    ASX Announcement 16 March 2007
    WNP Update
    The Company is pleased to update shareholders on the progress of drilling
    and work programs at the Windarra Nickel Project – WNP.
    Drilling has continued to intersect massive nickel sulphide mineralization at
    Denny Bore with NMD0004A intersecting two zones of massive sulphide
    mineralisation which are currently being logged and core cut for assay.
    Results will be released as soon as they become available.
    Drilling is currently proceeding on NMD0005 which is located approximately
    100 metres north-west of NMD0004 and is positioned to gain a further
    understanding of the geological setting which hosts the high grade nickel
    sulphide mineralization at Denny Bore. Progress has been slow due to poor
    rig performance and break-downs though this should now improve with the
    refurbishment of the main drilling engine completed. It is expected the target
    zone will be intersected in the coming week.
    The arrival of a second higher capacity diamond drill rig is scheduled for the
    June quarter and is currently being prepared for transport by float from
    Queensland to Kalgoorlie where it will undergo final hydraulic fit-out . It is
    intended that this second rig will be utilized to complete the NMD0001F
    DHTEM platform hole at Mt Windarra and to further define the high grade
    massive nickel sulphide mineralisation located beneath the historic workings
    at Mt Windarra.
    The Company is pleased to advise that Mr Steve Eggart has been appointed
    the initial mine manager. Steve comes to Niagara from the Norseman
    operations of Croesus Mining and will guide the mine development during the
    recommencement of operations. A little further down the track Steve will take
    on the permanent responsibility as underground manager.
    Mobilisation of the initial underground mining contract workforce is underway
    with the arrival this week of key underground mining personnel, equipment
    and stores. Erection of the heavy duty workshop is taking place and
    installation of the electrical workshop is complete. Niagara’s electrical
    supervisor, Arthur Anderson commenced duties at Windarra on Monday 12th
    March.
    The occupational, safety and health officer has been appointed and he will
    commence duties at Windarra on 2nd April. A fully equipped ambulance has
    been purchased and placed at Mt Windarra and, subject to our own

    Unit 8, Level 1, Churchill Court
    331-335 Hay Street
    Subiaco WA 6008
    PO Box 190
    West Perth WA 6872
    Tel: +61 8 9382 8799
    Fax: +61 8 9382 4760
    ABN 60 060 525 206
    operational requirements, will be available for emergencies in the district if
    required.
    The portal haulage road at Mt Windarra has been re-established and
    application for approval for re-entry to the mine decline to begin mine
    refurbishment is progressing.
    Independent resource calculations for the “G Shoot” at Mt Windarra, initially
    down to the 10200RL (approximately 200 metres below surface), are
    expected to be delivered late next week to assist in the mine planning now
    underway. Resource calculations for the entire Mt Windarra mine area are
    ongoing with digitization of historic exploration and mine records essentially
    completed.
    It is expected that G shoot will provide the first nickel ore from the WNP and
    the Company is currently in discussions with a number of parties interested in
    taking the product. First ore is scheduled to reach the surface in the
    September quarter.
    Installation of an extended power plant is underway. This is required for the
    expansion of on-site services and for the commencement of de-watering of
    the Mt Windarra mine and its refurbishment. Dewatering pumps have arrived
    on-site this week with installation down the historic Mt Windarra mine shaft
    scheduled to be completed by the month's end, subject to works approvals.
    Piping for discharging the mine water is ready to be laid to the northern
    tailings storage facility (NTSF) with welding due to commence shortly. It is
    expected de-watering will begin by the end of the current quarter and continue
    until the end of the calendar year or completion, whichever comes first. At this
    point the mine will be completely dewatered allowing for mining operations to
    proceed including decline development towards the high grade massive nickel
    sulphide zone identified below the historic Mt Windarra mine workings.
    Submission of the South Windarra Nickel Heap Leach proposal to relevant
    government departments has occurred and the Company awaits the outcome.
    As announced previously, our initial work will focus on the small (150,000
    tonnes) low-grade nickel sulphide stockpile situated on the northern side of
    the South Windarra pit. Test pits recently excavated from the surface of the
    adjacent dump has confirmed the presence of an even larger tonnage of
    nickeliferous material. Samples have been submitted for analysis and, whilst
    technically we must wait for the results, visual examination leads us to a
    confidence that the South Windarra Heap Leach project (SWHL) will expand
    to include the much larger tonnages of material available in the adjacent
    dump, as expected. At current nickel prices the cashflow projections are
    robust.
    Examination of other known nickel oxide resources is under way and we
    expect that this work will result in a substantial extension to the life of this
    operation at South Windarra.

    Unit 8, Level 1, Churchill Court
    331-335 Hay Street
    Subiaco WA 6008
    PO Box 190
    West Perth WA 6872
    Tel: +61 8 9382 8799
    Fax: +61 8 9382 4760
    ABN 60 060 525 206
    The Company looks forward to updating shareholders on the progress of its
    activities at the WNP over the coming weeks.
    Douglas C. Daws
    EXECUTIVE CHAIRMAN
    Note: The information in this report that relates to exploration results is based on information compiled by Mr
    Mick Elias, consulting geologist, who is a Fellow of the Australian Institute of Mining and Metallurgy. He has
    sufficient experience which is relevant to the style of mineralization and type of deposit under consideration, and to
    the activity undertaken. He is qualified as a competent person as defined in the 2004 Edition of the “Australian Code
    for Reporting Exploration Results, Mineral Resources and Ore Reserves”. He has consented to the inclusion of this
    information in the form and context in which it appears. The Australian Stock Exchange has not received and does
    not accept responsibility for the accuracy or adequacy of this release.
 