experimental roadkill? Like it... might have to try and apply that saying to everyday life
Kennedy project generator performance standard... looks like the battery was only a 2MW tesla unit, and perhaps as a result additional hardware was required to conform to grid standard.
https://reneweconomy.com.au/windlabs-solar-wind-battery-project-finally-connected-to-queensland-grid-41862/
I query those with more electrical engineering nouse (Ash - assuming this is your bag)... BESS and Hornsdale - would they currently have the additional physical assets mentioned in the above article??? or does their scale (25mw+) allow them to provide these functions? $25m for a single piece of hardware is material.
experimental roadkill? Like it... might have to try and apply...
Currently unlisted. Proposed listing date: 25 JUNE 2025 11:00 AM AEST ##
Add to My Watchlist
What is My Watchlist?