The latest WMRC meeting minutes are available here:
http://www.wmrc.wa.gov.au/documents/
Haven't had a chance to read it in detail but some quick notes:
Page 19: "To date full ramp up has not yet occurred and it appears highly unlikely to occur before May 2016. Accordingly, this budget review has been revised to take into account Brockwaste’s updated ramp up schedule which anticipates full capacity operation of the plant from May 2016 onwards."
Page 26: "The WMRC has a contractual obligation to deliver 33,000 tonnes of waste per year to Brockwaste, but only has approximately 14,500 tonnes of this waste available from its member councils. The waste supply agreement with the MRC is key in enabling the WMRC to meet its contractual commitments and avoid any penalties which may be incurred under the waste supply agreement with Brockwaste."
Interesting that up until June 2015 WMRC didn't have the waste to supply the plant!