    On 29th April 2020 - this was sent by NOPTA - Their recommendation to the JA together with 2 DRAFT 'Approval' letters .... and note how long they believed that the NSW and Commonwealth governments would take to make their decisions: (Yes - approx 2 weeks!!)

    "Delegates of the Commonwealth-New South Wales Offshore Petroleum Joint Authority for Decision
    29 April 2020

    NOPTA ADVICE
    1. Approve 24 months suspension to Permit Year 4 and a
    corresponding 24 months extension of the permit term in
    accordance with the Act and on merit.
    2. Approve a secondary variation to Permit Year 5 in accordance
    with the Act and Guideline.
    3. Convey the following to the applicant, via NOPTA:
    i) Condition 1 of the title remains in force, as such monthly
    reporting is still required; and that
    ii) The Joint Authority expects that the titleholders will meet
    with NOPTA within 12 months of this letter to discuss
    progress on approvals and contracting.
    A draft letter to the titleholder (Attachment 1) and a draft
    instrument (Attachment 2) reflecting the recommendations are
    provided with this assessment for your review.

    DECISION DUE
    State Delegate: 12 May 2020
    Commonwealth Delegate: 14 May 2020"