Quick summary below.
1) Drilled the 12.25" hole from casing point at 1874m to 2380m. Total 506m drilled since w'end.
2) 5 days lost due to Cyclone Dominic.
3) Due to buildup of another cyclone, rig is now being demanned. Operations will resume once this clears up.
A bit of a showstopper folks, but we are still 873m short of the first target Forestier Sands @ 3253m.
cheers