    I asked Brian a few questions about schedule.

    Dear Mr Park

    We have already completed the detailed capital costs for the Nueva Sabana mine and once we get the Mineral Resource Estimate for the mine the only thing that needs to be completed to finalise the PFS will be an estimate of the mining costs which will take a month.

    The DFS will produce the same or similar financial results but can’t be published until we have concentrate sales in place, and permitting which will take until April or May 2024.

    The DFS for the La Demajagua project can not be finished until we receive the quotation for the design and construction of the roaster and CIL circuit that have been added to the project.

    This will not occur until after the contractor completes 4 or 5 months of related metallurgical testwork.
    The current environmental approval also needs to be amended for the additional processing that will take place.

    Regards
 
watchlist Created with Sketch. Add AAU (ASX) to my watchlist
(20min delay)
Last
0.4¢
Change
0.000(0.00%)
Mkt cap ! $5.114M
Open High Low Value Volume
0.3¢ 0.4¢ 0.3¢ $3.864K 1.265M

Buyers (Bids)

No. Vol. Price($)
61 59401240 0.3¢
 

Sellers (Offers)

Price($) Vol. No.
0.4¢ 29148219 26
View Market Depth
Last trade - 15.55pm 31/07/2024 (20 minute delay) ?
AAU (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.