Operational Milestones
The Company previously reported the establishment of limited scale pre-production circulating flows
using existing chemical delivery systems. Well patterns in MU-1 are being pre-acidified and readied for
production operations. A booster pump has been received, installed, and commissioned to allow
significantly enhanced recirculation flowrates for preconditioning. Currently, an operation flowrate of
approximately 500 gallons per minute (GPM) has been established. Flowrates will continue to be
increased throughout May and June.
The large volume acid storage and distribution system is expected to be available for use by mid-May.
When commissioned, the new systems will facilitate higher concentrations of acid, further accelerating
the preconditioning operations.
Currently, the preconditioning process stream is not being directed to the production plant, and no
uranium is being recovered in the plant circuits. Uranium concentrations are expected to build throughout
the pre-conditioning operations, and it is currently projected that the process plant will be activated for
commercial uranium production activities by mid-year 2023.