Bear in mind that the final stages of evaporation take place after liming and the lime plant didn't come on line until mid last year.
Remember also that there was a pump selection problem.
I'm still struggling with the numbers - 82.8m USD equity and 191.9m USD debt financing = 274.7m USD. We're told the project came in on budget (229m USD capex), so what became of the 45m USD that was available to cover cost over runs and working capital?