Ian Chalmers was interviewed in local Dubbo paper today in relation to issue of Mining Lease and construction startup.
Summary of critical points
- mining lease hoped to be issued in a "few weeks"
- 46km water pipeline expected to be completed in March
- to start construction prior to water pipeline completed would require the company to "import water for dust control"
- delays to push production out to December or possibly January 2014
My take is that construction won't start until water pipeline is finished.
link to full article
http://www.dailyliberal.com.au/story/1239344/alkane-another-step-closer-to-start/?cs=112
- Forums
- ASX - By Stock
- where is the mining license?
Ian Chalmers was interviewed in local Dubbo paper today in...
-
- There are more pages in this discussion • 12 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
Add ALK (ASX) to my watchlist
(20min delay)
|
|||||
Last
43.8¢ |
Change
-0.003(0.57%) |
Mkt cap ! $267.0M |
Open | High | Low | Value | Volume |
44.0¢ | 45.0¢ | 43.3¢ | $1.309M | 2.978M |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
17 | 125475 | 43.5¢ |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
44.0¢ | 46880 | 12 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
17 | 125475 | 0.435 |
20 | 295366 | 0.430 |
11 | 88960 | 0.425 |
10 | 288073 | 0.420 |
4 | 16879 | 0.415 |
Price($) | Vol. | No. |
---|---|---|
0.440 | 46880 | 12 |
0.445 | 66455 | 5 |
0.450 | 42354 | 5 |
0.455 | 65346 | 9 |
0.460 | 114421 | 4 |
Last trade - 13.52pm 31/07/2024 (20 minute delay) ? |
Featured News
ALK (ASX) Chart |
The Watchlist
CCO
THE CALMER CO INTERNATIONAL LIMITED
Anthony Noble, CEO
Anthony Noble
CEO
SPONSORED BY The Market Online